California Builder & Engineer

Dedicated to the people who make our built environment better and safer. We tell your stories and celebrate your successes.

Register with us and receive industry news and content only available to subscribers.

Subscribe
Contacts

Indianapolis, IN, USA (HQ)

903 E. Ohio St., Indianapolis, IN 46202

Call: (317) 423-2325

info@acppubs.com

Restore the Corridor Increases Longevity for I-95 in Delaware

by: Larry Bernstein
Crews spread concrete on a section of I-95 as part of the Restore the Corridor project in Delaware.
Crews spread concrete on a section of I-95 as part of the Restore the Corridor project in Delaware.
Interstate 95 is a major north-south highway that runs the entire length of the United States and even makes its way into Canada. The route was developed in the mid-1950s, though the segment that runs through downtown Wilmington was originally built in 1964. Some portions of the roadway and bridges were widened in 1978, which included the construction of several on- and off-ramps. The Delaware Department of Transportation (DelDOT) is in the midst of the Restore the Corridor project to make sure commuters will continue to have a safe and smooth trip along I-95 in the future.

The 5-mile stretch of I-95 that the project covers is part of a critical East Coast corridor. It’s the main feeder to numerous ports, airports, trucking, freight transfer, and distribution centers, as well as a connection for millions of residents and visitors within an hour of the project segment. The average daily traffic count is approximately 110,000 vehicles, with 18 percent of the traffic being trucks. Therefore, keeping I-95 in good repair is a must. When a highway is 50-plus years old, things deteriorate and repairs are needed.

Widening the Scope
The Wilmington Viaduct Bridge and the Brandywine River Bridge are major bridges along I-95. Both bridges came up for work and needed significant repairs to extend bridge life. DelDOT determined each one on its own would require one and a half to two years of work. Shutting down sections of I-95 for four years was deemed not acceptable.

“We scoped the area and decided a corridor approach would be the most appropriate path forward,” says Jason Hastings, Chief of Bridges and Structures for DelDOT, who has worked on the project from concept until construction. “We were told we could only impact traffic for two years and decided to try and get as much done as possible in that time frame.”

Included in the project is the repair of 19 bridges, I-95 pavement, and ramps within the project limits are all part of the project.

Specifics include removing and replacing the top 2 inches of concrete on the bridge decks, resurfacing and repairing roadway, replacing deteriorating concrete traffic barriers and roadway expansion joints, painting the overpass bridges north of the Wilmington Viaduct, and completing steel and concrete repairs.

Gomaco
Your local Gomaco dealer
Terry Equipment

Hastings adds, “The 50-plus year old interstate has deteriorating lighting that is below standard, guard rails and other safety features that are not up to standards. All of those things will be brought up to a state of good repair, which adds a safety element to the project.” On that same note, two on-ramps that are high accident areas are being reconfigured to increase safety.

DelDOT did some advance projects prior to starting on the main work to lessen traffic impacts. The projects included resurfacing improvements and lane reconfigurations to Wilmington streets, upgrading traffic signals to better manage diverted traffic, as well as work on the Christina River Bridge and approaches.

Plotting the Way Forward
On the majority of DelDOT projects, they use the design-bid-build method. However, due to the sheer size and complexity of the Restore the Corridor project and the time constraints, DelDOT decided on a different method.

DelDOT elected to use the Construction Manager/General Contractor (CM/GC) method to build this project. In this method, the contractor becomes engaged in the project during the design phase. The contractor has input on the design and budget and can provide innovation and expertise on how to construct the project.

Kiewit won the bid for preconstruction and later won the bid to be the contractor during construction. Donald Arant, who served as the preconstruction manager of Kiewit and is in an executive role during construction, noted this type of delivery method inspires a full partnership and gives the contractor an opportunity to impact design and mitigate risks.

Arant and the Kiewit team have already done two major actions that have impacted construction. The project was originally scheduled to have nine major phases, but “we got it down to two major phases, which has cost benefits and positively impacts the schedule,” says Arant. The second action was related to powerlines that are under a bridge that Amtrak uses. “We have experience working with Amtrak and were able to develop a demo shield innovation and not move the power lines which mitigated a significant risk. Plus, we completed the installation of the demo shields before major construction began,” says Arant.

Construction Challenges
“On a rehab job, unlike brand new construction, things can pop up, such as a utility in an unexpected place, that slow things down,” says Kevin Lindell, the Project Manager with DelDOT. “The way we’re handling these types of issues is by focusing on communication.”
Deere CE
Your local Deere & Co dealer
Coastline Equipment

Lindell, design consultants, and Kiewit personnel are all in the same office building. They all ride the job every day looking for issues that may come up. When something comes up, it is discussed right away, and a solution is quickly found.

Access to the work zone is also a challenge. Again, I-95 is heavily trafficked in the area, so getting the massive quantities of materials needed for the job to and from the site is time-consuming. “We transfer materials to and from the site at night,” Arant says. The team also does some demolition offsite when possible.

Similarly, Lindell notes driving through the entire job is no longer possible – without getting on the remaining open lanes of I-95 – due to all the various activities occurring. “We created access points to facilitate the movement of the team.”

To ensure smooth construction, the team is using hydro demolition machines. The machine sprays water at a very high pressure to demolish the concrete. The water is calibrated to remove the desired amount of depth. This accelerated construction technique leaves a nice surface so it gets a good bond.

Collaboration Saves Time and Money
The project began in February and is expected to be complete in the spring of 2023. The project is on schedule and the team is aiming to get it done early and meet the original challenge of two years.

The project has a budget of $205 million (including contingencies) and is being funded by the state via a Grant Anticipation Revenue Vehicle bond (GARVEE). The Federal Highway Association says of GARVEE bonds, “Specific to highways, a GARVEE is used as a term for a debt instrument that has a pledge of future Title 23 Federal-aid funding. Significantly, it is authorized for Federal reimbursement of debt service and related financing costs.” The federal government paid 80 percent of the budget for the design phase.

Gomaco
Your local Gomaco dealer
Terry Equipment

So far, the project is on budget. Lindell credits the CM/GC delivery method and Kiewit. They’ve helped by identifying potential risks, creating a risk register, and assigning a value if the risk comes to pass.

Avant adds, “CM/GC drives a true partnership and fosters collaboration.”

When the corridor is restored, commuters will have a roadway that is in good condition. Rather than having to regularly attend to this section of I-95, DelDOT will have extended the life of the highway and made it safer for commuters.

SITECH
Your local Trimble Construction Division dealer
SITECH Southwest
SITECH West
Gomaco
Your local Gomaco dealer
Terry Equipment
SITECH
Your local Trimble Construction Division dealer
SITECH Southwest
SITECH West